A contractor employed sixty men to face a certain work and get it completed in fifteen days. If the number of labourers is to be increased to two hundred and twenty five, working at the same rate, how long will the work take them?

Options

A) 2 days

B) 16 days

C) 4 days

D) 12 days

The correct answer is C.