Use the information below to answer the question that follows: .
Prime cost..................₦12 100
Lighting....................₦10 000
Heating.....................₦15 000
Factory overhead............?
The production department share of factory overhead is 1/4 and 1/2 of lighting and heating respectively.
The factory overhead is?
Options
A)
₦5050
B)
₦7250
C)
₦2750
D)
₦5500

The correct answer is D.
More Past Questions:
Discussion
Other Subjects
- English Language
- Biology
- Government
- Mathematics
- Physics
- Economics
- Chemistry
- Christian Religious Knowledge
- Commerce
- Geography
- Literature In English
- Agricultural Science
- General Paper
- History
- Islamic Religious Knowledge
- Further Mathematics
- Current Affairs
- Computer Studies
- Civic Education
- Math
- Reading
- Writing and Language
- Home Economics
- French
- Igbo
- Hausa
- Yoruba
- Fine Arts
- Basic Accounting